Prop S (2021)

Thank you voters! Prop S passed!

Prop S: Safe Schools, Safe Kids

The Mehlville School District Board of Education voted unanimously at its Jan. 21, 2021, meeting to place a zero tax rate increase bond issue measure on the ballot on April 6, 2021. The community voted to approve the bond issue on April 2, 2021.

The bond issue, called Proposition S, is funding projects to improve student safety and accessibility and complete deferred maintenance without increasing the tax rate.

Prop S is funding security entrances at every school; improved accessibility for individuals with disabilities; heating, cooling and ventilation upgrades; restroom renovations and additions; parking lot improvements; roof replacements and other projects.

Prop S generated more than $35 million to complete these projects without raising the current tax rate. Voter approval allowed the district to transfer 12 cents of the existing tax rate to address facility needs at all schools within the Mehlville School District at no additional cost to the taxpayer.

What our community has told us

Beginning in January 2019, the Facility Steering Committee began work to identify necessary facilities needs at each of our campuses. The committee included community members, parents and staff representing each of our 19 schools. Together, the committee surveyed parents, students and staff and visited each school to see facility needs firsthand and to prioritize facility projects. The committee also heard reports about the known backlog of maintenance work on school roofs and HVAC systems. Through Facility Steering Committee feedback forms and surveys related to our strategic plan, safety emerged as the community’s top priority for its schools. In addition to safety, the Facility Steering Committee also heard that accessibility, restrooms and parking lots were a concern. The projects that are being funded by Prop S represent the most pressing facility needs as identified by the committee.

Prop S Progress

The project list for Prop S was originally created in 2020 based on the recommendations of the district's Facilities Steering Committee. In 2020, district estimates indicated that these projects could be completed for $32 million. The district asked voters for a bond issue in the amount of $35 million to provide a financial cushion for unexpected expenses and inflation.

Mehlville School District was able to sell $35 million in bonds at a premium, netting an additional $2.7 million. However, due to rapidly escalating construction costs and supply chain delays, $37.7 million was not enough to complete all of the Prop S projects. Projects that were eliminated or delayed are referenced below.  Some of the delayed projects are being paid for using capital funds, as indicated with an asterisk. 

Beasley Elementary School

Project

Status
Security entrance Completed
HVAC replacement Completed
Restrooms Delayed
Outdoor lighting* In Progress
Driveway and parking lot expansion Delayed

Bierbaum Elementary School

Project Status
Security entrance Completed
Additional classrooms, expanded library and storm shelter Completed
ADA accessibility to classrooms near the office Completed
Restroom renovations Completed
Expanded front parking lot Completed
Perimeter fencing Completed
Outdoor lighting* In Progress

Blades Elementary School

Project Status
Security entrance Completed
Outdoor lighting*

In Progress

Forder Elementary School

Project Status
Security entrance Completed
HVAC replacement Completed
Outdoor lighting* In Progress

Hagemann Elementary School

Project Status
Security entrance Completed
ADA access to playground Completed
Additional parking lot entrance Delayed

MOSAIC Elementary School

Project Status
Security entrance Completed
Elevator In Progress

Oakville Elementary School

Project Status
Security entrance Completed
Expanded parking lot with more accessible parking Completed

Point Elementary School

Project Status
Security entrance Completed
ADA accessibility to back door Completed

Rogers Elementary School

Project Status
Security entrance Completed
Parking lot and playground safety improvements Completed
HVAC replacement Completed

Trautwein Elementary School

Project Status
Security entrance Completed
Roof replacement (82 squares) Completed
Parking lot improvements Delayed
Outdoor lighting* In Progress

Wohlwend Elementary School

Project Status
Security entrance Completed
Additional ADA accessible parking Completed
ADA accessibility to art and music rooms Delayed
Outdoor lighting* In Progress

Bernard Middle School

Project Status
Security entrance Completed
Outdoor lighting* In Progress

Buerkle Middle School

Project Status
Security entrance Completed
Roof replacement (463 squares) Completed
Restroom additions and renovations* In Progress
Accessibility to track Delayed
Outdoor lighting* In Progress

Oakville Middle School

Project Status
Security entrance Completed
Outdoor lighting* In Progress

Washington Middle School

Project Status
Security entrance Completed
Renovate main entrance to improve accessibility Completed
Roof replacement (365 squares) Completed
Outdoor lighting* In Progress

Mehlville High School

Project Status
Security entrance Completed
Baseball and softball field safety upgrades Completed
HVAC replacement Completed
ADA accessibility to band room Delayed
Parking lot and walkway improvements Delayed
New restrooms at stadium* Eliminated from Prop S project list as of June 2022

Oakville High School

Project Status
Security entrance Completed
Upgraded restrooms at stadium Completed
Restroom renovations Completed
Baseball and softball field safety upgrades Completed
Roof replacement (662 squares) Completed

John Cary Early Childhood Center

Project Status
Security entrance Completed
HVAC replacement Completed

Transportation

Project Status
New transportation office and garage* Eliminated from Prop S project list as of June 2022